Capital Improvement Contracts Summary |
|
---|
CMSA's current CIP contracts are listed below. The cost listed for each project includes all fees |
CONTRACT NO. |
CONTRACT NAME SLUDGE THICKENING SYSTEM REPLACEMENT PROJECT – ENGINEERING SERVICES |
|
DESCRIPTION Provide engineering services for the replacement of the two existing dissolved air flotation thickeners (DAFs) with two rotary drum thickeners (RTDs), modifications to piping and polymer supply systems to connect to the new RDTs, and integration of the new equipment into the treatment plant process control system. |
||
AWARDED TO HDR Engineering, Inc. |
ORIGINAL COST $347,157.00 |
|
AWARDED DATE 09/11/2013 |
END DATE |
CONTRACT NO. 14 - 07 |
CONTRACT NAME SCADA INTEGRATION SUPPORT SERVICES |
|
DESCRIPTION |
||
AWARDED TO Carollo Systems, Inc. |
COST Scope and fee set by individual Task Order |
|
AWARDED DATE 09/12/2013 |
END DATE |
CONTRACT NO. |
CONTRACT NAME CHEMICAL STORAGE ROOM REHABILITATION PROJECT – ENGINEERING SERVICES |
|
DESCRIPTION |
||
AWARDED TO Carollo Engineers, Inc. |
ORIGINAL COST $38,323.00 |
|
AWARDED DATE 12/31/2013 |
END DATE |
CONTRACT NO. |
CONTRACT NAME CHEMICAL STORAGE ROOM REHABILITATION PROJECT – CONSTRUCTION |
|
DESCRIPTION Rehabilitation work involves removing and replacing the damaged concrete and rebar, replacing the chemical piping system, and installing a new, non-skid epoxy coating. |
||
AWARDED TO Pacific Infrastructure Corporation |
ORIGINAL COST $1,035,060.00 |
|
AWARDED DATE 03/04/2015 |
END DATE 10/10/2015 |
CONTRACT NO. |
CONTRACT NAME ELECTRICAL DISTRIBUTION SYSTEM, ARC FLASH, AND NFPA 820 EVALUATIONS |
|
DESCRIPTION Reconcile previous electrical studies, perform a condition assessment of the main facility switchgear, and conduct an NFPA 820 evaluation for areas in and around the treatment plant. |
||
AWARDED TO Carollo Engineers, Inc. |
ORIGINAL COST $111,256.00 |
|
AWARDED DATE 06/13/2014 |
END DATE 06/30/2015 |
CONTRACT NO. |
CONTRACT NAME CONSTRUCTION MANAGEMENT SUPPORT |
|
DESCRIPTION Provide construction management support services for Agency selected capital improvement and asset management projects. Services may include performing design document constructability and biddability reviews; regular and specialty construction inspections and preparation of field inspection reports; review and evaluation of submittals, change order requests, and construction schedules; and other construction management services as requested. |
||
AWARDED TO Dee Consultants, LLC |
ORIGINAL COST Scope and fee set by individual Task Order |
|
AWARDED DATE 06/10/2014 |
END DATE |
CONTRACT NO. |
CONTRACT NAME SLUDGE THICKENING SYSTEM REPLACEMENT PROJECT – CONSTRUCTION |
|
DESCRIPTION Project scope of work includes the replacement of the two existing dissolved air flotation thickeners (DAFs) with two rotary drum thickeners (RTDs), modifications to piping and polymer supply systems to connect to the new RDTs, and integration of the new equipment into the treatment plant process control system. |
||
AWARDED TO Mountain Cascade |
ORIGINAL COST $ 1,780,250.00 |
|
AWARDED DATE 12/01/2014 |
END DATE |
CONTRACT NO. |
CONTRACT NAME ODOR CONTROL SYSTEM IMPROVEMENTS – ENGINEERING SERVICES |
|
DESCRIPTION Provide engineering services for the selection of the appropriate rehabilitation or replacement technology for each of the treatment plant’s three original odor scrubbing units, and prepare final plans and specifications for public bidding. |
||
AWARDED TO Brown and Caldwell |
ORIGINAL COST $ 324,751 |
|
AWARDED DATE 11/25/2014 |
END DATE |
CONTRACT NO. |
CONTRACT NAME ARCHITECTURAL DESIGN AND SUPPORT SERVICES |
|
DESCRIPTION Provide facility architectural design and support services for various Agency projects. Initial services include program level assistance to plan the expansion and remodeling of the Maintenance Building and Maintenance Annex to better meet the Agency’s office space and equipment and supply storage needs. |
||
AWARDED TO FME Architecture + Design |
ORIGINAL COST $16,900.00 |
|
AWARDED DATE 11/11/2014 |
END DATE |